The easiest way to compare work amounts with your original plan is to apply the Work table to a sheet view, such as the Gantt Chart view or Resource Usage view. You can compare work amounts for tasks as a whole, or for resources and their individual assignments. This helps you assess whether work on your project is progressing as expected.

What do you want to do?Īs you track progress through your project, you can review the differences between planned, scheduled, and actual work. As your project progresses, you can review how work on its tasks is affecting the overall project schedule.